All the experts suggest IT candidates to prepare from a valid source to avoid any kind of misinformation. The most popular study stuff among It students and experts is CMRP dumps. This expertly written stuff gives you brief explanation of each exam topic and broadens your knowledge of the field. It is a matter of few clicks to download this study material from Realexamdumps. But before any such undertaking, you can get free demo questions from the same place for quality clearance. You will get excellent command over the discipline by studying from CMRP questions and answers. Once you get prepared from this material, there will be no chance of failure. It ascertains your success in getting CMRP Certification by providing you money back guarantee. Passing guarantee makes you eligible to claim your payment back in case of unsatisfied results after using CMRP dumps. For more info: https://www.realexamdumps.com/smrp/cmrp-practice-test.html
PDF CMRP Dumps Exam Question - Money Back Guarantee | Realexamdumps
S M R P CMRP Dumps
CMRP Maintenance & Reliability Professional
For More Info:
https://www.realexamdumps.com/smrp/cmrp-practice-test.html
SMRP CMRP : Practice Exam
Question No : 1
The Weibull distribution with a shape factor less than 1 is associated with burn in or early
life failures that could be caused by:
A. Poor quality assurance.
B. Irregular loading.
C. Increasing strength.
D. Improper assembly.
Answer: B
Question No : 2
For which of the following elements is the maintenance manager directly responsible?
A. Equipment failure probability
B. Equipment operating practices
C. Life cycle costs of equipment
D. Optimization of maintenance costs
Answer: D
Question No : 3
A maintenance manager has a spreadsheet list of all of the equipment failures that have
occurred at the plant (facility) over the past three years. Which of the following analytical
methods or tools might be used to sort and prioritize the list?
A. Root Cause Failure Analysis
B. Life Cycle Cost Analysis
C. Total cost of ownership
D. Pareto Analysis
Answer: D
Question No : 4
2
SMRP CMRP : Practice Exam
Examples of workplace ethics issues include everything except:
A. whistle-blowing.
B. pay raises.
C. conflicts of interest.
D. workplace privacy.
Answer: B
Question No : 5
What is one of the significant achievements of predictive maintenance programs?
A. Permitting the ordering of long lead-time parts when the equipment breaks
B. Minimizing use of components that are designed to wear out
C. Increased awareness of and less uncertainty concerning machinery condition
D. Providing delayed information about equipment condition after the equipment has failed
Answer: C
Question No : 6
What is at the heart or core of the Organization for International Standards (ISO) 9000
series documents concerning quality of products and services?
A. Management of quality assurance processes
B. Human safety and environmental protection
C. How to write quality control documents
D. Procedures, document existence, compliance, and control
Answer: D
Question No : 7
Themost effective method of performance evaluation is:
A. a field review process.
3
SMRP CMRP : Practice Exam
B. a behaviorally anchored rating scale process
C. a employee written assessment.
D. a feedback process.
Answer: B
Question No : 8
How do you avoid the pitfall of the Maintenance and Reliability Program appearing to have
littlevalue to the organization?
A. Implement all available predictive technology techniques
B. Use a systematic approach to ensure business goals drive the effort
C. Establish a comprehensive communication program including e-mail web page, and
newsletter
D. Claim the success of the company is directly related to the Maintenance and Reliability
program
Answer: B
Question No : 9
A Company produced 80.000 tons of "Good Product" last year, and the Sales department
has projected a 5% increase in sales during the coming year. Production Statistics:
1.The production line operates 24 hours per day. seven days per week, except for the
downtime listed below.
2.The production line downtime for maintenance averaged 108 hours per month during the
past year.
3.The production line was shut down three times during the year due to power
interruptions, for a total of 18 hours of downtime.
4.The production operators' union has threatened a strike that may last as long as three
weeks if it occurs.
5.The production rate is expected to stay the same as last year's production rate.
6.Power interruption downtime is expected to stay the same as last year.
4
SMRP CMRP : Practice Exam
B. a behaviorally anchored rating scale process
C. a employee written assessment.
D. a feedback process.
Answer: B
Question No : 8
How do you avoid the pitfall of the Maintenance and Reliability Program appearing to have
littlevalue to the organization?
A. Implement all available predictive technology techniques
B. Use a systematic approach to ensure business goals drive the effort
C. Establish a comprehensive communication program including e-mail web page, and
newsletter
D. Claim the success of the company is directly related to the Maintenance and Reliability
program
Answer: B
Question No : 9
A Company produced 80.000 tons of "Good Product" last year, and the Sales department
has projected a 5% increase in sales during the coming year. Production Statistics:
1.The production line operates 24 hours per day. seven days per week, except for the
downtime listed below.
2.The production line downtime for maintenance averaged 108 hours per month during the
past year.
3.The production line was shut down three times during the year due to power
interruptions, for a total of 18 hours of downtime.
4.The production operators' union has threatened a strike that may last as long as three
weeks if it occurs.
5.The production rate is expected to stay the same as last year's production rate.
6.Power interruption downtime is expected to stay the same as last year.
4
SMRP CMRP : Practice Exam
Based on the Production Statistics shown, what is the required production line availability
to meet the sales projected for next year?
A. 86.50%
B. 88.50%
C. 89.50%
D. 93.50%
Answer: C
Question No : 10
As the maintenance manager for a manufacturing company, you have conducted a study
that reveals the mechanics, on average, spend four hours per ten hour shift on wrench time
(tool turning time). Your first action should be:
A. Improve planning and scheduling to increase wrench time (tool turning time).
B. Encourage your planners to develop more aggressive job estimates.
C. Inform management that four hours wrench time (tool turning time) per day is
considered good.
D. Investigate the barriers causing loss of wrench time (tool turning time).
Answer: D