If you are going to appear in PMI-100 exam then you can prepare from PMI-100 dumps to bring the best grades out of your efforts. You will get your desired grades with money back guarantee because the quality of this dumps material cannot be challenged. PMI-100 dumps material is the most suitable material for the preparation of this certification. It has been designed by considering the nature and requirements of exam and students’ inclination towards learning.https://www.realexamcollection.com/pmi/pmi-100-dumps.html
2020 Valid PMI PMI-100 Exam Questions
Vendor: PMI
Exam Code: PMI-100
Exam Name: Certified Associate in Project
Management(CAPM)
Version: Demo
https://www.realexamcollection.com/pmi/pmi-100-dumps.html
Topic 1, Volume A
Question No : 1 - (Topic 1)
Which document defines how a project is executed, monitored and controlled, and closed?
A. Strategic plan
B. Project charter
C. Project management plan
D. Service level agreement
Answer: C
Question No : 2 - (Topic 1)
Which changes occur in risk and uncertainty as well as the cost of changes as the life cycle
of a typical project progresses?
A. Risk and uncertainty increase; the cost of changes increases.
B. Risk and uncertainty increase; the cost of changes decreases,
C. Risk and uncertainty decrease; the cost of changes increases.
D. Risk and uncertainty decrease; the cost of changes decreases.
Answer: C
Question No : 3 - (Topic 1)
Which tool or technique is used in the Plan Scope Management process?
A. Document analysis
B. Observations
C. Product analysis
D. Expert judgment
Answer: D
Question No : 4 - (Topic 1)
2
Which tool or technique is an examination of industry and specific vendor capabilities?
A. Independent estimates
B. Market research
C. Analytical techniques
D. Bidder conferences
Answer: B
Question No : 5 - (Topic 1)
An input used in developing the communications management plan is:
A. Communication models.
B. Enterprise environmental factors.
C. Organizational communications,
D. Organizational cultures and styles.
Answer: B
Question No : 6 - (Topic 1)
Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA),
and trend analysis are examples of which tool or technique?
A. Expert judgment
B. Forecasting methods
C. Earned value management
D. Analytical techniques
Answer: D
Question No : 7 - (Topic 1)
The Perform Quality Assurance process occurs in which Process Group?
A. Executing
3
B. Monitoring and Controlling
C. Initiating
D. Planning
Answer: A
Question No : 8 - (Topic 1)
Enterprise environmental factors are an input to which process?
A. Control Scope
B. Define Scope
C. Plan Scope Management
D. Collect Requirements
Answer: C
Question No : 9 - (Topic 1)
Which process develops options and actions to enhance opportunities and reduce threats
to project objectives?
A. Identify Risks
B. Control Risks
C. Plan Risk Management
D. Plan Risk Responses
Answer: D
Question No : 10 - (Topic 1)
The process of establishing the policies, procedures, and documentation for planning,
developing, managing, executing, and controlling the project schedule is known as:
A. Plan Schedule Management.
B. Develop Project Charter.
C. Develop Schedule.
4