Have you chosen out generally our new associations? Indeed, it is starting and quit around its assessment C_ACTIVATE05 Dumps praised among more energetic individuals nowadays. We classify as clear with IT is particularly a bewildering control and an unquestionably important strategy. Along with New Year's pleasure, you can acquire a flat 30% OFF on all the exams. You can gain this chance by using Coupon Code: "D4D30NY21".
Up to 30% Off On 2021 C_ACTIVATE05 Dumps PDF - Dumps4download
SAP
C_ACTIVATE05
SAP Certified Associate -
SAP Activate Project Manager
https://www.dumps4download.com/c-activate05-dumps.html
Get Prepared And Pass
Verified By Experts
Your Exam.
SAP - C_ACTIVATE05
Question #:77
What are deliverables of the Application: Integration work stream in the prepare phase?
There are 3 correct answers to this question.
Response:
A. Fit/Gap Analysis
B. Data Cleansing
C. Security Checks
D. Adaptation Specifications
E. Network Connectivity Checks
Answer: C D E
Question #:54
What is the purpose of a firm-up sprint?
Please choose the correct answer.
Response:
A. To demonstrate functionality from previous sprint
B. To perform sprint testing
C. To revise a release plan and sprint plan
D. To run end-to-end integration test
Answer: B
Question #:44
What does SAP Activate recommend to keep team members informed and aligned?
Please choose the correct answer.
Response:
A. Daily status meeting with project manager
B.
1 of 4
SAP - C_ACTIVATE05
B. Daily team stand-up meeting
C. Daily e-mail status updates to project manager
D. Daily progress review meeting with sponsor
Answer: B
Question #:3
What is a difference between the SAP Activate methodology for a new implementation of SAP S/4HANA
cloud edition and a new implementation of SAP S/4HANA on-premise?
Please choose the correct answer.
Response:
A. For the cloud edition, there is an additional work stream for integration with on-premise systems
B. For the cloud edition, there is an additional Q-Gate for integration with on-premise systems
C. For on-premise, there is an additional Q-Gate for system installation
D. For on-premise, there are additional deliverables for the system setup
Answer: D
Question #:13
How can SRCUM teams be organized?
Please choose the correct answer.
Response:
A. By job title
B. By work stream
C. By project phase
D. By project governance level
Answer: B
Question #:74
Which content packages are available in the SAP Package Library?
2 of 4
SAP - C_ACTIVATE05
There are 2 correct answers to this question.
Response:
A. SAP Activate Methodology
B. SAP Best Practices
C. Solution Builder
D. Rapid Deployment Solutions
Answer: B D
Question #:1
Which activities are part of the Application: Solution Adaption work stream of SAP Activate for new
implementations?
There are 3 correct answers to this question.
Response:
A. Value Audits
B. Production Support Plan
C. Value Determination
D. Change Management Plan
E. Scope Validation
Answer: A C D
Question #:36
In which phase of the SAP Activate methodology does the team complete the Cut-over Rehearsal?
Please choose the correct answer.
Response:
A. Prepare
B. Explore
C. Realize
3 of 4
SAP - C_ACTIVATE05
D. Deploy
Answer: D
Question #:53
Which of the following is a Key Deliverable of the Prepare phase?
Please choose the correct answer.
Response:
A. Solution Scope and Value Determination
B. Change Impact Analysis and Communication Plan
C. Baseline Build
D. Release and Sprint Plan
Answer: A
Question #:16
When do you perform User Acceptance Testing during the Agile Build?
Please choose the correct answer.
Response:
A. Before Integration Testing
B. During each Firm-up Sprint
C. After each Sprint
D. After Integration Testing
Answer: D
4 of 4